Perils and prospects of the Jaitapur Nuclear Power Project in India
The protest against the 9900-MWe Jaitapur Nuclear Power Project, the largest engineering project ever conceived in Maharashtra, India, is gathering momentum. But the Rs.1 lakh-crore project is likely to be implemented as it has already received environmental clearance and the Union government is determined to double nuclear energy generating capacity by 2020. As part of the commitment to climate change, the government plans to change the proportion of energy mix. At present, nuclear energy accounts for nearly three per cent of our electricity generating capacity.
Today, 38 per cent of India’s greenhouse gas emission comes from the power sector and the government feels a pressing need for cleaner energy options.
Even though nuclear energy option reduces greenhouse gas emissions, the protest is mainly on account of other concerns.
The Jaitapur project will come up in collaboration with French giant Areva, which will supply uranium and reactor units, according to the Nuclear Power Corporation of India Limited.
On 26.11.2010, the Ministry of Environment & Forests accorded environmental clearance for the 6×1650 MWe nuclear power project in Jaitapur, Maharashtra. Union Minister of State for Environment and Forests Jairam Ramesh announced the environmental clearance with 35 conditions and safeguards.
Extensive opposition to the project, particularly from the Konkan Bachao Samiti (KBS), was overruled by the government in granting this clearance.
The Environment minister however clarified that it could take on board only the ecological objections raised by the protesters. It has asked the Nuclear Power Corporation of India Limited and its partner Areva to address the other economic, commercial, safety and technological issues. Areva is a predominantly state-owned nuclear power company in France, which has developed the 1650 MWe European Pressurised Reactor (EPR), based on the French N4 and the German Konvoi reactor types.
But concerns have been raised on the maturity of the EPR technology as no EPR has been constructed and commissioned for operation anywhere in the world. Four EPRs are in different stages of construction and two of them are facing serious problems. The construction of the first EPR to Finland started in 2005 and construction and design problems have delayed the start-up of this plant to the second half of 2013 which is a delay of 3.5 years and a cost escalation of 50 per cent.
The second EPR construction in France was in December 2007. Similar construction and safety issues have led to a 50 per cent cost increase and a delay of commissioning to 2014.
China bought two EPRs for which the completion dates are 2013 and 2014.
As the EPR is allegedly in trouble, the French government asked Francois Roussely, a former chairman of the Electricite de France (EDF), in October 2009 to evaluate the status of the EPR and the French nuclear industry. The Roussely Report of July 2010 has concluded that the credibility of the EPR has been seriously damaged by the problems of the two reactors under construction.
According to the report, the complexity of the EPR comes from (questionable) design choices, notably of the power level, containment, core-catcher, and redundancy of systems.
The first of the six units of 1650 MWe capacity each is expected to be commissioned by 2017-18. It will help Maharashtra reduce its energy deficit. Nearly 1000 hectares of land has already been acquired for the project.
To address the grievances of the local community, the State government had formed an Empowered Group of Ministers to enhance the compensation.
The process of environmental clearance by the union ministry of environment has tried to balance four objectives: the amount of energy required to sustain a growth rate of nine per cent; the proportion of fuel mix; strategic diplomacy, especially after the Civilian Nuclear Deal; and the environmental concerns raised by a large number of groups.
The protest against the 9900-MWe Jaitapur Nuclear Power Project, the largest engineering project ever conceived in Maharashtra, India, is gathering momentum. But the Rs.1 lakh-crore project is likely to be implemented as it has already received environmental clearance and the Union government is determined to double nuclear energy generating capacity by 2020. As part of the commitment to climate change, the government plans to change the proportion of energy mix. At present, nuclear energy accounts for nearly three per cent of our electricity generating capacity.
Today, 38 per cent of India’s greenhouse gas emission comes from the power sector and the government feels a pressing need for cleaner energy options.
Even though nuclear energy option reduces greenhouse gas emissions, the protest is mainly on account of other concerns.
The Jaitapur project will come up in collaboration with French giant Areva, which will supply uranium and reactor units, according to the Nuclear Power Corporation of India Limited.
On 26.11.2010, the Ministry of Environment & Forests accorded environmental clearance for the 6×1650 MWe nuclear power project in Jaitapur, Maharashtra. Union Minister of State for Environment and Forests Jairam Ramesh announced the environmental clearance with 35 conditions and safeguards.
Extensive opposition to the project, particularly from the Konkan Bachao Samiti (KBS), was overruled by the government in granting this clearance.
The Environment minister however clarified that it could take on board only the ecological objections raised by the protesters. It has asked the Nuclear Power Corporation of India Limited and its partner Areva to address the other economic, commercial, safety and technological issues. Areva is a predominantly state-owned nuclear power company in France, which has developed the 1650 MWe European Pressurised Reactor (EPR), based on the French N4 and the German Konvoi reactor types.
But concerns have been raised on the maturity of the EPR technology as no EPR has been constructed and commissioned for operation anywhere in the world. Four EPRs are in different stages of construction and two of them are facing serious problems. The construction of the first EPR to Finland started in 2005 and construction and design problems have delayed the start-up of this plant to the second half of 2013 which is a delay of 3.5 years and a cost escalation of 50 per cent.
The second EPR construction in France was in December 2007. Similar construction and safety issues have led to a 50 per cent cost increase and a delay of commissioning to 2014.
China bought two EPRs for which the completion dates are 2013 and 2014.
As the EPR is allegedly in trouble, the French government asked Francois Roussely, a former chairman of the Electricite de France (EDF), in October 2009 to evaluate the status of the EPR and the French nuclear industry. The Roussely Report of July 2010 has concluded that the credibility of the EPR has been seriously damaged by the problems of the two reactors under construction.
According to the report, the complexity of the EPR comes from (questionable) design choices, notably of the power level, containment, core-catcher, and redundancy of systems.
The first of the six units of 1650 MWe capacity each is expected to be commissioned by 2017-18. It will help Maharashtra reduce its energy deficit. Nearly 1000 hectares of land has already been acquired for the project.
To address the grievances of the local community, the State government had formed an Empowered Group of Ministers to enhance the compensation.
The process of environmental clearance by the union ministry of environment has tried to balance four objectives: the amount of energy required to sustain a growth rate of nine per cent; the proportion of fuel mix; strategic diplomacy, especially after the Civilian Nuclear Deal; and the environmental concerns raised by a large number of groups.
By GLOBAL IAS TEAM
